A trusted source of Asia-Pacific commercial aviation news and analysis


SEPTEMBER 2021

Week 36

News

Hong Kong International Airport third runway reaches pavement milestone

next article »

« previous article


 

September 8th 2021

Print Friendly

Airport Authority Hong Kong (AA) said yesterday the pavement work had been completed for Hong Kong International Airport's (HKIA) new third runway. Read More » A ceremony marking the event was held with AA chairman, Jack So, invited guests and media. "With the completion of reclamation and runway pavement works, we are confident the new runway will commence operations next year as planned," So said. "Other works, including expansion of Terminal 2 (T2), construction of the T2 Concourse, a new automated people mover system and a high-speed baggage handling system will be completed in 2024 on schedule and within budget." Construction of the third runway, which will lift HKIA's annual capacity to 120 million passengers and 10 million tonnes of cargo when completed, began in 2016. The airport handled 71.5 passengers in 2019 and 74.7 million in 2018.

next article »

« previous article






Response(s).

SPEAK YOUR MIND

Your email address will not be published. All fields are required.

* double click image to change